RECREATION AMENITIES ENHANCEMENT PROJECT
We’re moving right along! Last month the Rec Amenities team met with contractors and selected one they recommended to the NSCA Board. By June 30, we hope to have finalized and awarded the contract. Stay tuned!
At their June 14 meeting, the Board approved design modifications needed to keep project costs within budget while still providing the major features of the plan.
At this time, construction will begin the week after Labor Day and is expected to be complete by year end. Next month we will provide more information related to the construction activities and the associated restrictions on access to our existing facilities.
Have a safe and happy 4th of July!
—Debi Berk
Post a Comment